A practical breakdown of the typical timeline for this job type. Actual time varies with drawing clarity, tolerances, finishing, and shipping method.
Quotation
0.5 day
Review drawings, confirm material/finish, and provide a costed quote with lead time and assumptions.
DFM + Confirmation
0.5–1 day
Confirm tolerances, critical features, datums, and inspection requirements to prevent rework.
Material Procurement
1–3 days
Source SS304 stock, verify certs if required, and prepare blanks for machining.
Programming + Setup
1 day
CAM programming, tooling selection, workholding plan, and first-article setup.
Machining
5–8 days
Production machining with in-process checks to hold key dimensions and surface finish.
Finishing
1–3 days
Deburr, edge break, and surface finish processing as specified.
Inspection + Packing
0.5–1 day
Final inspection, documentation as requested, protective packaging for transit.
Shipping
3–7 days
Dispatch via express or economy service depending on budget and delivery target.